Enterprise IP CCTV, Access Control & 30-Day Storage Audit Checklist
DORI optical field-of-view metrics, RAID storage architecture, biometric access calibration, and fire-life safety integration.
Stage 1: Optical Camera Placement & DORI Metrics
Pass Inspection Item / Parameter Standard / Reference Recommended Acceptance / QA Criteria
Detection, Observation, Recognition IEC 62676-4 Guidelines Camera FOV calibrated to DORI reference densities: Detection (25 px/m), Observation (63 px/m), Recognition (125 px/m).
Identification Target Density IEC 62676-4 / Project QA Identification: Target pixel density of approximately 250 px/m at designated identification zones, subject to camera optics, lighting, scene geometry and project acceptance testing.
Stage 2: Network Infrastructure & Storage Architecture
Pass Inspection Item / Parameter Standard / Reference Recommended Acceptance / QA Criteria
Video Retention Duration Project / Police Norms Continuous 30-day recorded video retention at full frame rate (25 FPS) on RAID-5/6 array, where applicable, with zero dropped frames.
PoE Switch Bandwidth & Power Budget IEEE 802.3at PoE+ Maximum camera draw within 70% of total PoE switch power capacity; packet loss < 0.1%.
Stage 3: Physical Access Control & Emergency Integration
Pass Inspection Item / Parameter Standard / Reference Recommended Acceptance / QA Criteria
Reader Communication Protocol SIA OSDP v2 Standard Encrypted bi-directional OSDP v2 communication between readers and access control panels.
Fire Alarm Emergency Release Life Safety Interlock Fail-safe magnetic locks automatically de-energize and release immediately upon Fire Alarm signal to ensure unimpeded egress.
Final Commissioning & Handover Sign-Off
Client Representative / Facility Head:

Name: ___________________________________

Company: ________________________________

Site Location: ___________________________

Signature & Date: _______________________
Certified Turnkey EPC Partner:

RS Electricals & HVAC Solutions

Senior Commissioning Engineer: ________________

Enlistment: Punjab Class-A Electrical Contractor

Helpline: +91 62399-13625 / +91 62399-13625
Classification of Technical Values: Numerical values identified as “Typical Engineering Design Targets” or “Recommended Acceptance / QA Criteria” are project-specific engineering benchmarks and company acceptance criteria. They are not necessarily universal statutory limits. Final requirements shall be determined from the applicable current edition of the governing standard, project specification, equipment manufacturer requirements and competent authority approvals.