NBC 2016 Part 4 Fire NOC & Hydrant-Sprinkler Commissioning Checklist
Hydrostatic riser integrity, pump sequencing, terminal pressure verification, and life safety automated interlocks for commercial and industrial facilities.
Stage 1: Fire Water Storage & Pumping Station
Pass Inspection Item / Parameter Standard / Reference Recommended Acceptance / QA Criteria
Dedicated Fire Water Storage NBC 2016 Part 4 Table 7 Underground / terrace static water storage exclusively reserved for firefighting with automated level monitoring.
Jockey, Main & Diesel Pump Sequencing IS 12469 / NFPA 20 Automatic cut-in sequence: Jockey cuts in at 6.0 bar; Main electric cuts in at 5.0 bar; Diesel pump automatic crank start on mains electrical blackout or pressure drop to 4.0 bar.
Pump Flow & Head Performance IS 15301 / NFPA 20 Rated discharge delivery at 100% and 150% load without cavitation; diesel battery double-bank float charger verified.
Stage 2: Hydrostatic Pressure & Hydraulic Distribution
Pass Inspection Item / Parameter Standard / Reference Recommended Acceptance / QA Criteria
Riser Hydrostatic Pressure Testing NFPA 13 / IS 15105 Hydrostatic test at 200 psi / 13.8 bar or 50 psi above working pressure (whichever greater) maintained for 2 hours with allowable leakage limits rather than an arbitrary zero-drop assumption.
Terminal Residual Running Pressure IS 3844 / NBC 2016 Minimum residual pressure of 3.5 kg/cm² (bar) at highest/farthest yard hydrant; ≥ 2.5 kg/cm² at remotest sprinkler head with required simultaneous streams flowing.
Sprinkler Array & Zone Control IS 15105 Hazard-based sprinkler hydraulic density, quartzoid bulb rating (68°C standard), flow switch zone signaling to main Fire Alarm Panel.
Stage 3: Life Safety System Interlocks & Passive Protection
Pass Inspection Item / Parameter Standard / Reference Recommended Acceptance / QA Criteria
Fire Alarm (FAS) Polling & Notification IS 2189 100% addressable smoke/heat detector polling response < 10 seconds; manual call points functional.
HVAC AHU Trip & Damper Actuation NBC 2016 Part 4 Immediate automatic shutdown of all ventilation AHUs; motorized fire/smoke dampers close on alarm signal.
Fire-Mode Elevator Recall Approved Fire Strategy / NBC Fire-mode elevator recall/return to the designated fire-service or egress level, where required by the approved fire strategy and applicable code.
Escape Egress & Door Hardware IS 3614 / NBC 2016 2-hour fire-rated doors with panic crash bars; magnetic door release de-energizes immediately upon fire signal; PA-EVAC emergency voice broadcast priority.
• Statutory Mandate: Physical inspection and live pump demonstration are required by Punjab Fire Services / Municipal Fire Authorities prior to issuing Provisional and Final Fire Safety NOC.
Final Commissioning & Handover Sign-Off
Client Representative / Facility Head:

Name: ___________________________________

Company: ________________________________

Site Location: ___________________________

Signature & Date: _______________________
Certified Turnkey EPC Partner:

RS Electricals & HVAC Solutions

Senior Commissioning Engineer: ________________

Enlistment: Punjab Class-A Electrical Contractor

Helpline: +91 62399-13625 / +91 62399-13625
Classification of Technical Values: Numerical values identified as “Typical Engineering Design Targets” or “Recommended Acceptance / QA Criteria” are project-specific engineering benchmarks and company acceptance criteria. They are not necessarily universal statutory limits. Final requirements shall be determined from the applicable current edition of the governing standard, project specification, equipment manufacturer requirements and competent authority approvals.