Turnkey MEP Pre-Execution BOQ Audit & Clash Detection Checklist
Federated 3D BIM clash detection, tender quantity verification, Life Cycle Cost Analysis, and statutory milestone tracking.
Stage 1: 3D BIM Spatial Coordination & Clash Detection
| Pass |
Inspection Item / Parameter |
Standard / Reference |
Recommended Acceptance / QA Criteria |
|
Multi-Disciplinary Clash Resolution |
ISO 19650 / Company QA |
Federated model clash runs between Electrical cable trays, HVAC ductwork, Fire piping, and structure: Zero unresolved critical/hard clashes as company coordination acceptance criterion. |
|
Service Access & Maintenance Clearances |
NBC 2016 / ASHRAE |
Adequate physical clearance verified for valve operation, filter pulling, and transformer withdrawal. |
Stage 2: BOQ Quantity Take-Off & Commercial Due Diligence
| Pass |
Inspection Item / Parameter |
Standard / Reference |
Recommended Acceptance / QA Criteria |
|
Quantity Verification |
Company Commercial Benchmark |
Physical drawing take-off compared against tender BOQ with variance control target strictly within ± 3%. |
|
Life Cycle Cost Analysis (LCCA) |
ASHRAE / Energy Engineering |
10-year operating expenditure (OPEX) evaluated against initial capital expenditure (CAPEX) for chillers, transformers, and VFDs. |
Stage 3: Equipment Prequalification & Statutory Milestone Tracking
| Pass |
Inspection Item / Parameter |
Standard / Reference |
Recommended Acceptance / QA Criteria |
|
Factory Test Certificates |
Project Specification Matrix |
Review and verification of type test certificates from accredited laboratories (CPRI / ERDA / AHRI / UL) as dictated by project specifications. |
|
Statutory Authority Milestone Tracking |
Punjab & Central Authorities |
Schedule tracking for PSPCL (Power), CEIG (Electrical), Fire Services (Fire NOC), and PPCB (Pollution Control). |
Final Commissioning & Handover Sign-Off
Client Representative / Facility Head:
Name: ___________________________________
Company: ________________________________
Site Location: ___________________________
Signature & Date: _______________________
Certified Turnkey EPC Partner:
RS Electricals & HVAC Solutions
Senior Commissioning Engineer: ________________
Enlistment: Punjab Class-A Electrical Contractor
Helpline: +91 62399-13625 / +91 62399-13625
Classification of Technical Values: Numerical values identified as “Typical Engineering Design Targets” or “Recommended Acceptance / QA Criteria” are project-specific engineering benchmarks and company acceptance criteria. They are not necessarily universal statutory limits. Final requirements shall be determined from the applicable current edition of the governing standard, project specification, equipment manufacturer requirements and competent authority approvals.