NABH Hospital OT HVAC & Cleanroom Validation Protocol
Environmental airflow validation, HEPA filtration integrity, pressure differentials, and thermal parameters for surgical suites and healthcare cleanrooms.
Stage 1: Central Chiller Plant & Hydronic Commissioning
Pass Inspection Item / Parameter Standard / Reference Recommended Acceptance / QA Criteria
Chilled Water Delta-T Verification AHRI 550/590 / ASHRAE 90.1 Entering/leaving water temperature verified at 7°C supply / 12.5°C return (typical design ΔT 5.5°C to 6.0°C).
Evaporator & Condenser Approach Recommended QA Benchmark Approach temperature targeted < 1.5°C under steady full-load operation.
Hydronic Flow Balancing ASHRAE Handbook Dynamic balancing valve differential pressure manometry within ±10% of design flow rate.
Stage 2: Ductwork Integrity & Air Distribution
Pass Inspection Item / Parameter Standard / Reference Recommended Acceptance / QA Criteria
Duct Leakage Testing SMACNA HVAC Air Duct Leakage Class-C duct leakage test at 1.5x operating pressure with leakage rate within SMACNA allowable limits.
Airflow Balancing & Diffuser CFMs ASHRAE 111 Hood anemometer measurement at supply/return diffusers within ±10% of design specification.
Stage 3: Surgical Suite & Healthcare OT Environmental Criteria
Pass Inspection Item / Parameter Standard / Reference Recommended Acceptance / QA Criteria
Air Change Rate (ACPH) NABH 5th Edition / ASHRAE 170 Type-A Major OT: Minimum 20 ACH total air changes, with minimum 4 fresh-air outdoor ACH.
Healthcare OT Pressure Relationship ASHRAE 170 / NABH Guidelines Healthcare OT Pressure Relationship: Minimum positive pressure differential of ≥ 2.5 Pa, with project-specific cascade values (typically +10 to +15 Pa) established through the approved HVAC design.
Temperature & Relative Humidity NABH / Clinical Guidelines Temperature 21°C ± 2°C; Relative Humidity 45%–55%, subject to OT category and surgical preference.
HEPA Filter In-Situ Integrity ISO 14644-3 / IEST In-situ DOP/PAO aerosol challenge leak test: penetration < 0.01% through terminal H14 HEPA (99.995% @ 0.3µm) filter media and frame seals.
Particle Count & Recovery Decay Time ISO 14644-1 / ISO 14644-2 Particle concentration compliant with ISO Class 7 at rest; contamination recovery decay time back to baseline < 15 minutes.
• Clinical Notice: Operating theatre environmental parameters are established to ensure patient safety, surgical site infection control, and staff comfort. Validation protocols must be repeated annually or after any major AHU/filter maintenance.
Final Commissioning & Handover Sign-Off
Client Representative / Facility Head:

Name: ___________________________________

Company: ________________________________

Site Location: ___________________________

Signature & Date: _______________________
Certified Turnkey EPC Partner:

RS Electricals & HVAC Solutions

Senior Commissioning Engineer: ________________

Enlistment: Punjab Class-A Electrical Contractor

Helpline: +91 62399-13625 / +91 62399-13625
Classification of Technical Values: Numerical values identified as “Typical Engineering Design Targets” or “Recommended Acceptance / QA Criteria” are project-specific engineering benchmarks and company acceptance criteria. They are not necessarily universal statutory limits. Final requirements shall be determined from the applicable current edition of the governing standard, project specification, equipment manufacturer requirements and competent authority approvals.